Project Overview
Phase 2 executed installation and commissioning of the 12-inch HDPE condensate line: pipeline laying and jointing from the Power Plant to the Injection Well, flow and integrity testing, and handover for live condensate duty.
Key Deliverables
- Pipeline laying and jointing, Power Plant to Injection Well
- Flow testing and integrity inspection
- Commissioning and operational handover
Technical Specifications
Anggaran (Budget)
USD 485,000
Lokasi (Location)
๐
Star Energy Geothermal (Wayang Windu) Limited
Tahun Pelaksanaan
2014
Client
Star Energy Geothermal