Project Overview
Phase 1 covered route engineering and material procurement for the 12-inch HDPE condensate line: field survey, route design from the Power Plant to the Injection Well, and supply of HDPE pipe and fittings.
Key Deliverables
- Route survey and detailed pipeline design
- Procurement of 12-inch HDPE pipe and fittings
- Phase-1 site preparation and logistics
Technical Specifications
Anggaran (Budget)
USD 313,453
Lokasi (Location)
๐
Star Energy Geothermal (Wayang Windu) Limited
Tahun Pelaksanaan
2014
Client
Star Energy Geothermal